Cost Estimate

Facility $4,593k
Mirrors $2,443k
OSS, Covers, & Positioners $3,521k
Peripherals & Slow Control $146k
PMTs & Bases $1,223k
High Voltage $747k
Focalplane Instrumentation $940k
Telescope Trigger (L1) $308k
Flash ADC $3,054k
Telescope Pattern Trigger (L2) $732k
Central Array Trigger (L3) $173k
Central Array Pattern Trigger (L4) $196k
Cables & Connectors $253k
Timing $84k
Calibration $522k
Data Acquisition $367k
Data Analysis $35k
Data Archiving $136k
Project Office $1,294k
Total $20,768k


 